This page gives a map of the progress of the project so far. The primary goals will be completed first as they are necessary to complete the project. Secondary goals are an expansion of the project to increase the usefulness.
As we make progress towards these goals, we note the changes made each revision and link to notes on that revision under each goal it effects.
Primary Goals (50%)
Wiki framework (100%)
Rev No1
Rev No2
Tutorial (50%)
Mathew’s Build and Test (75%)
Rev No1
Rev No4
Rev No5
Rev No7
Bart’s Build and Test (25%)
Josiah’s build and Test (50%)
Coppied Tutorial Information(30%)
Rev No8
Corrections/Updates to previous Tutorials (10%)
Rev No8
Expanded Build Process Descriptions (0%)
Subversion Repositories (100%)
Rev No0
Tarballs (0%)
Current – External tutorials (0%)
Current – External tutorials (30%)
Built (75%)
Rev No1
Tested (0%)
Packaged (0%)
Secondary Goals (0%)
Linux 2.6 (N/A)
On board build environment (N/A)
Building new drivers (N/A)
Revised on April 10, 2007 16:40:52
by
Matthew