This page gives a map of the progress of the project so far. The primary goals will be completed first as they are necessary to complete the project. Secondary goals are an expansion of the project to increase the usefulness.

As we make progress towards these goals, we note the changes made each revision and link to notes on that revision under each goal it effects.

Primary Goals (50%)

Best Known Build Process Documentation (50%)

Wiki framework (100%)

Rev No1

Rev No2

Tutorial (50%)

Mathew’s Build and Test (75%)

Rev No1

Rev No4

Rev No5

Rev No7

Bart’s Build and Test (25%)

Josiah’s build and Test (50%)

Coppied Tutorial Information(30%)

Rev No8

Corrections/Updates to previous Tutorials (10%)

Rev No8

Expanded Build Process Descriptions (0%)

Best Source Code (50%)

Subversion Repositories (100%)

Rev No0

Tarballs (0%)

Current – External tutorials (0%)

Best Binaries (30%)

Current – External tutorials (30%)

Built (75%)

Rev No1

Tested (0%)

Packaged (0%)

Secondary Goals (0%)

Linux 2.6 (N/A)

On board build environment (N/A)

Building new drivers (N/A)

Revised on April 10, 2007 16:40:52 by Matthew